LCTID Project/Traffic Updates week of 10/26/26

October 23, 2026

Please see below the LCTID Project Update for the Week of October 26, 2026:

Duncan Plains Road – County Line to Clover Valley

Construction: Three pipe crews continue on storm sewer installation. The full-depth pavement reclamation work will continue until mid-week, after which stone base will be placed for the road. Asphalt pavement will be installed the following week.

Traffic: County Line Road will be closed between Blamer and Needles. Residents should use Edwards to Clover Valley to travel east of the project.

County Line Road

Construction: Two box culverts will be installed between Blamer and Montgomery in the next two weeks. The contractor will need to dig footers, place wingwalls, place the box sections, waterproof, and then backfill the structure.

Traffic: October 19 the road will be closed at the northern location (see attachment). October 26 the road will be closed at the southern location. Two-way traffic will be maintained north and south of the closures.

Fancher Road / County Line Road Intersection
Closed through November 2026 for Delaware County TID roundabout construction.

Traffic: Use the map’s red route detour.

Mink Road / Duncan Plains Road Intersection

Construction: Grading and storm sewer are complete. Underdrain to drain the road base is now complete. The aggregate base for the road is 20% complete and will continue next week. Survey layout for curb is done, concrete curb will be slipformed next week.

Traffic: Intersection closed through December 2026. The purple route detour is unchanged.

Clover Valley Road

Construction: October 19 the contractor will begin performing pavement repairs. They will begin on Clover Valley from US-62 to Green Chapel Road. Mid-week they will switch to the section between Duncan Plains and SR-37. The contractor plans to then complete milling, intermediate asphalt, and surface asphalt all in the southern section before moving to the northern section.

Traffic: The contractor will close one lane in their work area and maintain two-way traffic in the open lane with flaggers. Information about the project has been sent to significant construction projects in the area. We have requested they divert their site labor from commuting on Clover Valley; however, delays should be expected in the work areas during rush hours.